166 Million Yuan! GHPE and Xi’an Datang Sign For 52MW Distributed PV Project

PVTIME – On February 23, Wuxi Huaguang Environment & Energy Group Co.,Ltd.(600475.SH) announced that its holding subsidiary GHPE’s subsidiary Xi’an Datang Electric Power Design Research Institute Co., Ltd. has signed with Xi’an Rongsheng New Energy Co.,Ltd.for 52MWp distributed photovoltaic power generation project with a total investment of 166 million yuan.

The project is planned to start on February 20, 2022, and the construction period is expected to be 190 days. The planned completion date is June 30, 2022 for the rooftop area and August 30, 2022 for the carport area.

Huaguang Environment & Energy Group stated that this project will provide the company more experience in the photovoltaic power project, improving the company’s market competitiveness, and enhance the market influence of Xi’an Datang Electric Power Design Research Institute as well.