PVTIME – On 21 October 2024, Tongwei won the solar module tender of Guohua Energy Investment Co., Ltd, a subsidiary of Chinese energy giant CHN Energy.
The target project is part of the first phase (1GW) of Huohua’s 3GW large-scale solar power plant in Xinjiang, China, with an installed capacity of 300MW on the AC side, a capacity ratio of 1.2084 and an installed capacity of 362.05208MWp on the DC side.
The winning bid was 239,678,476.96 Yuan at a unit price of 0.662 Yuan per Watt. The supply capacity is not less than 362.05208MWp of 593528 pieces of n-type 610Wp double-sided double-glazed monocrystalline silicon PV modules. The delivery period is from January 2025 to June 2025.