Brazil Cancels Previously Postponed 2020 New Energy Auctions, Announces Schedule for 2021-2023 Triennium

PVTIME – On Tuesday, the Brazilian Ministry of Mines and Energy (MME) issued two ordinances which outlined the cancellation of its previously indefinitely postponed A-4 and A-6 energy auctions while revealing the schedule for new energy auctions throughout the 2021 – 2023 triennium.

According to the ordinances, the 2021 A-3 and A-4 energy auctions will contract power from wind, solar, biomass and hydropower sources, while the A-5 and A-6 tenders will also include coal, natural gas, and solid urban waste projects.

The new schedule is as follows:

Date

Auction

June 2021

A-3 and A-4

September 2021

A-5 and A-6

April 2022

A-4

September 2022

A-6

April 2023

A-4

September 2023

A-6

 

 

 